How Hoima city spent Shs1b that anguished MP Nyakato

The key part of the report to the Hoima City Works Committee Meeting that never went well on Tuesday was coverage of the roads mapped for rehabilitation in Hoima City.

The authorities say the expenditure was dependent upon the time of fund reception and the endorsed work plan.

The report below was released by Ms Margaret Monday, the Secretary for Works, Hoima City Council who said that the funds spent were part of the Shs1b allocated to Hoima city for Financial Year 2023/24.

She said the funds came in two phases – each delivering 50% and was used accordingly as per the work plan.

The accountability was, however, disputed by the Hoima City Woman Member of Parliament, Ms Asinansi Nyakato, who cited shoddy work and elements of embezzlement that resulted  in a clash ending the meeting prematurely.

According to the report seen by Kazi-njema News, the planned expenditure for the 4km Kibiingo-Kyabalyanga Road was Shs143.69m. However, Shs136.49m was the expenditure and the network stands at 100% completion.

The 5.5km Kyedikyo-Buliindi-Kasomoro Road was planned at an expenditure of Shs147.486m while Shs140.286m was spent and stands at 100% completion.

The planned expenditure on the 2.3km Kasingo-Kasasa Road stood at Shs71.183m but Shs63.9832m was spent and stands at 85% completion as the 3km Kicwamba-Butebere Road that was planned at an expenditure of Shs93.007m had Shs85.807m spent on it and completion stands at 85%.

The planned expenditure for the 2km Kyakadongo Road was Shs91.735m, no expenditure has so far been made and works will commence this quarter.

The 4.6km Kiduma-Kirubika-Kabalyanga Road was planned at an expenditure of Shs137.69m, no expenditure has so far been made and work will commence this quarter.

The 5km Kasingo-Kigarama Road planned expenditure stands at Shs154.472m, expenditure is yet to be effected and work will begin this quarter.

The expenditure for the 3.2km Karongo-Budaka Road stands at Shs109.505m and work will also begin this quarter while the Busiisi-Kasasa-Ruyanja Road planned expenditure stood at Shs48.2m, the same amount that was spent on it and all civil works are complete.